Estimating bidding practice questions

30 questions from the contractor business and law practice test.

Beta. These questions are new and are being checked by licensed tradespeople. If one looks wrong, use “Report this question” and we will fix it.

Estimating bidding practice test

10 questions, graded as you go, with the reason for every answer. No sign-up.

What this covers

Sample questions

How many cubic yards of concrete are needed for a slab 40 ft long, 30 ft wide and 6 in. thick? Do not add waste.

Answer in cubic yards.

Show the answer

22.22 cubic yards

Thickness = 6 in. = 0.5 ft. Volume = 40 x 30 x 0.5 = 600 cu ft. 600 / 27 = 22.22 cu yd.

Reference: Estimating principles: volume takeoff, 27 cu ft per cu yd

A continuous footing is 2 ft wide, 1 ft deep and 180 ft long. With a 5% waste allowance, how many cubic yards of concrete should be ordered?

Answer in cubic yards.

Show the answer

14 cubic yards

Volume = 2 x 1 x 180 = 360 cu ft. 360 / 27 = 13.33 cu yd. With waste: 13.33 x 1.05 = 14.0 cu yd.

Reference: Estimating principles: volume takeoff with waste factor

A room is 20 ft by 15 ft with 8 ft walls. Ignoring openings, how many 4 ft x 8 ft drywall sheets are needed for the walls only, allowing 10% waste? Round up to a whole sheet.

Answer in sheets.

Show the answer

20 sheets

Perimeter = 2 x (20 + 15) = 70 ft. Wall area = 70 x 8 = 560 sq ft. Sheet = 4 x 8 = 32 sq ft. 560 / 32 = 17.5 sheets. With waste: 17.5 x 1.10 = 19.25, round up to 20 sheets.

Reference: Estimating principles: wall area takeoff and waste