Asphalt shingles are being installed on a 3:12 roof under the IRC. Compared with a 6:12 roof, what must change?
- Underlayment goes on in two layers
- Shingle exposure is cut in half
- Shingles are fully bedded in cement
- Six nails are used in each shingle
Show the answer
A. Underlayment goes on in two layers
Between 2:12 and 4:12 water drains slowly and can back up under the tabs, so the code calls for a doubled underlayment. Extra nails address wind, not slow drainage, and the exposure does not change.
Reference: IRC 2021 R905.1.1 and R905.2.2
Under the IRC, the minimum number of fasteners for a standard asphalt strip shingle in a normal application is:
- 2
- 3
- 6
- 4
Show the answer
D. 4
Strip shingles take at least four fasteners each, or more where the manufacturer requires. Six nails is the usual high-wind or very steep slope pattern, not the base requirement.
Reference: IRC 2021 R905.2.6
Which roofing nail meets the IRC minimum for fastening asphalt shingles?
- 16-gauge shank with a 1/4 in. head
- 12-gauge shank with a 3/8 in. head
- 14-gauge shank with a 5/16 in. head
- 10-gauge shank with a 1/4 in. head
Show the answer
B. 12-gauge shank with a 3/8 in. head
The code calls for corrosion-resistant roofing nails with at least a 12-gauge shank and a 3/8 in. diameter head. A heavier shank with a small head still fails because the head is what holds the shingle against pull-through.
Reference: IRC 2021 R905.2.5