✓ TradeExamPro

TradeExamPro › Contractor

Contractor business and law practice test

249 free practice questions for this exam, each with the reason for the answer and where to look it up.

Beta. These questions are new. They were written and checked with AI and have not yet been reviewed by a licensed tradesperson. If one looks wrong, use “Report this question” and we will fix it.

Contractor business and law: practice test

10 questions, graded as you go, with the reason for every answer. No sign-up.

Practice tests that prepare you for this exam

About the exam

ExamContractor business and law
Who runs itState boards, NASCLA
WhereUnited States (varies by state)

Question count, time limit and pass mark differ by where you take it. Check the official candidate bulletin from the organisation that runs your exam.

Sample questions

Two contractors form a general partnership. One partner signs a supply contract for a partnership job and the bill goes unpaid. Who can the supplier collect from?

  1. Only the partner who signed the contract
  2. The partnership and either partner personally
  3. Only the partnership's own bank accounts and equipment
  4. Each partner, but only for half of the bill
Show the answer

B. The partnership and either partner personally

Each general partner is an agent of the partnership and is personally liable for partnership debts, so the supplier can pursue the firm and either partner for the full amount. Liability is not limited to the signing partner or split in halves as far as the creditor is concerned.

Reference: Uniform Partnership Act: general partner agency and joint and several liability

Which statement describes a cost-plus-fee contract?

  1. The owner pays one fixed price regardless of the actual costs incurred
  2. The owner pays a set price for each measured unit of work
  3. The owner pays only after a certificate of occupancy is issued
  4. The owner reimburses actual costs and pays the contractor a fee
Show the answer

D. The owner reimburses actual costs and pays the contractor a fee

In a cost-plus contract the owner pays the documented cost of the work plus a fixed or percentage fee for overhead and profit, so the owner carries the cost risk. A fixed price regardless of cost is a lump-sum contract.

Reference: Contract types: cost-plus-fee contract

How many cubic yards of concrete are needed for a slab 40 ft long, 30 ft wide and 6 in. thick? Do not add waste.

Answer in cubic yards.

Show the answer

22.22 cubic yards

Thickness = 6 in. = 0.5 ft. Volume = 40 x 30 x 0.5 = 600 cu ft. 600 / 27 = 22.22 cu yd.

Reference: Estimating principles: volume takeoff, 27 cu ft per cu yd

Taking this exam?

Tell us where and when you are taking it, and what you want more of. It decides what we write next.

Other contractor exams with practice tests

NASCLA accredited commercial general building contractor · Residential builder / residential contractor · General / building contractor · Roofing contractor · Concrete / masonry contractor · Solar contractor · Lead renovator (RRP) · Lead abatement worker / supervisor