At what maximum interval must a working scaffold be inspected by a competent person?
Every 24 hours
Every 7 days
Every month
Every 6 months
Show the answer
B. Every 7 days
A scaffold is inspected before first use, after any alteration, damage or severe weather, and at intervals not exceeding 7 days, with the result recorded. A monthly or 6-monthly interval is far too long for a structure that changes and weathers.
Reference: Safety, Health and Welfare at Work (General Application) Regulations 2007 (S.I. 299/2007), Part 4 (work at height) and Schedule on scaffold inspection
What is the minimum height of the top guardrail on a working platform edge?
600 mm
750 mm
950 mm
1.5 m
Show the answer
C. 950 mm
The top guardrail must be at least 950 mm above the working platform. A lower rail catches a person above their centre of gravity and allows them to tip over it.
Reference: Safety, Health and Welfare at Work (General Application) Regulations 2007 (S.I. 299/2007), Part 4 (work at height) and Schedule on guardrails
What is the minimum height of a toe board on a scaffold platform edge?
50 mm
75 mm
100 mm
150 mm
Show the answer
D. 150 mm
A toe board of at least 150 mm stops tools and materials rolling or being kicked off the platform onto people below. A shallower board is easily overtopped.
Reference: Safety, Health and Welfare at Work (General Application) Regulations 2007 (S.I. 299/2007), Part 4 (work at height) and Schedule on toe boards