Sample questions
A site has 40 workers. What is the minimum emergency health provision for a site of 50 workers or fewer?
A full-time physician
A certified first-aider
A full-time registered nurse and a dentist
A site infirmary with one bed
Show the answer
B. A certified first-aider
Sites of 50 workers or fewer need a certified first-aider. A nurse is required starting at 51 workers, and a physician only at larger sizes.
Reference: DOLE DO 13 s.1998 (Guidelines on OSH in the Construction Industry), Sec. 8.1
A building project employs 150 workers. Which emergency health provision applies?
A part-time first-aider only
A full-time physician and a dentist
A full-time registered nurse
A one-bed infirmary
Show the answer
C. A full-time registered nurse
A workforce of 51 to 200 needs a full-time registered nurse. A first-aider alone is enough only up to 50 workers, and physicians and infirmaries come at higher headcounts.
Reference: DOLE DO 13 s.1998 (Guidelines on OSH in the Construction Industry), Sec. 8.1
A worker dies in a dangerous occurrence on site. Within what time must the employer notify the DOLE Regional Office?
Within 24 hours
Within 7 days
By the end of the same month
Within 30 days
Show the answer
A. Within 24 hours
A death or permanent total disability from a dangerous occurrence or major accident is notified to the DOLE Regional Office within 24 hours. The monthly report is not a substitute for this notice.
Reference: DOLE DO 13 s.1998 (Guidelines on OSH in the Construction Industry), Sec. 14