Sample questions
A notice of commencement is recorded on 1 February and does not state an expiration date. The job runs well past one year. What does the lien law say about the notice?
It lapses after one year unless it states a later date
It stays effective until the certificate of occupancy is issued
It stops being effective 90 days after recording
It never expires once it has been recorded
Show the answer
A. It lapses after one year unless it states a later date
A notice of commencement without a stated expiration lapses one year after it is recorded. For a longer job the owner should list a later date, or the notice no longer works as the base for lien rights.
Reference: Fla. Stat. 713.13(6)
An owner records a notice of commencement, but the contractor does not actually begin work for four months. What is the effect on the notice?
It stays effective for the full one-year default period
It is effective only for liens of the general contractor
It is effective as long as the building permit is still open
It is ineffective because work did not start within 90 days
Show the answer
D. It is ineffective because work did not start within 90 days
The notice of commencement is tied to real work starting. If the improvement does not actually begin within 90 days after recording, the notice is ineffective and a new one must be recorded.
Reference: Fla. Stat. 713.13(2)
A general contractor wants to file suit to enforce its own lien. How far ahead of starting the action must it give the owner its contractor's final payment affidavit?
At least 30 days before starting the action
At least 5 days before starting the action
At least 10 days before starting the action
The affidavit is not needed for a contractor's own lien
Show the answer
B. At least 5 days before starting the action
The contractor must give the owner the final payment affidavit when final payment is due, and no later than 5 days before it starts an action to enforce its lien. A longer lead time such as 30 days is not what the statute sets.