What is a snap tie designed to do after the forms are stripped?

  1. Pull out of the wall in one whole piece
  2. Stay sticking out of the wall to hold insulation
  3. Break off a short distance inside the wall face
  4. Be cut off flush with the wall surface
Show the answer

C. Break off a short distance inside the wall face

Snap ties have a weakened point so the ends break back inside the concrete surface, leaving a small hole to patch. Ties that pull out whole are tapered or she-bolt ties.

Reference: ACI 347R, form ties

In a job-built wall form, what are the horizontal members that back up the studs and take the load to the ties called?

  1. Shores
  2. Sills
  3. Spreaders
  4. Walers
Show the answer

D. Walers

Walers (wales) run horizontally across the studs, keep the form aligned and carry the pressure to the ties. Shores are vertical supports under slab and beam forms.

Reference: ACI 347R, wall form components

A groove is formed along the top of a footing before the wall is placed on it. What is it for?

  1. To drain the bleed water off the footing
  2. To hold the vertical dowels in position
  3. To mark the centreline for the form crew
  4. To key the wall to the footing against sliding
Show the answer

D. To key the wall to the footing against sliding

A keyway lets the wall concrete lock into the footing so the joint resists lateral shear from soil or other side loads.

Reference: Formwork details: keyed construction joints