What is a snap tie designed to do after the forms are stripped?
Pull out of the wall in one whole piece
Stay sticking out of the wall to hold insulation
Break off a short distance inside the wall face
Be cut off flush with the wall surface
Show the answer
C. Break off a short distance inside the wall face
Snap ties have a weakened point so the ends break back inside the concrete surface, leaving a small hole to patch. Ties that pull out whole are tapered or she-bolt ties.
Reference: ACI 347R, form ties
Which mortar type has the highest compressive strength and is suited to heavily loaded masonry and work below grade?
Type N
Type O
Type K
Type M
Show the answer
D. Type M
Type M is the strongest, about 2500 psi under the property specification, and is used for foundations, retaining walls and heavy loads. Type N is a medium-strength mortar for above-grade work.
Reference: ASTM C270, mortar types
Concrete for a footing will be in contact with soil that has a very high sulfate content. Which portland cement type gives the highest sulfate resistance?
Type I
Type V
Type II
Type III
Show the answer
B. Type V
Type V is the high-sulfate-resistance cement. Type II is the tempting choice, but it only gives moderate sulfate resistance and is meant for moderate exposure.
Reference: ASTM C150, portland cement types
How many cubic yards of concrete are needed for a slab 20 ft by 30 ft and 4 in. thick? Do not add waste.
Answer in cu yd.
Show the answer
7.41 cu yd
Thickness = 4/12 = 0.333 ft. Volume = 20 x 30 x 0.333 = 200 cu ft. 200 / 27 = 7.41 cu yd.
Reference: Concrete estimating: volume in cubic yards
Which practice is best when placing concrete in a slab?
Dump it in one pile and drag it out with rakes
Dump it in one pile and move it along with a vibrator
Start at the middle and push it to the edges
Deposit it as close as possible to its final position
Show the answer
D. Deposit it as close as possible to its final position
Concrete should be placed as near as possible to where it will stay. Dragging it or flowing it with a vibrator makes the mortar run ahead of the stone and causes segregation.