Home Improvement Contractor and Salesperson Practice Test
Practice questions on residential remodeling contracts, consumer protection, liens and payment, licensing, insurance and basic remodeling knowledge. State-specific rules are named in the question; the rest rests on federal rules and common practice.
Prices are in US dollars, plus tax where it applies. Stripe, our payment processor and the seller of record, adds tax at checkout.
All sales are final. If something is really wrong, such as a duplicate charge or a purchase that does not unlock what you bought, write to support@tradeexampro.com and we will put it right.
One-time payment. Nothing renews.
You have an exam ticket for this practice test. Start the mock exam to use it.
Which of these sales is covered by the FTC Cooling-Off Rule?
A $20,000 deck contract signed at the contractor's permanent showroom after negotiating there
A $15 smoke alarm sold at the homeowner's door
A $4,800 siding contract signed at the homeowner's kitchen table after an unsolicited visit
A pipe repair the homeowner phoned in, with a handwritten, dated, signed emergency waiver
Show the answer
C. A $4,800 siding contract signed at the homeowner's kitchen table after an unsolicited visit
An unsolicited visit that ends in a $4,800 sale at the buyer's home is above the $25 threshold and covered. Sales negotiated at a permanent place of business, sales under the threshold, and buyer-initiated emergencies with a proper waiver are excluded.
Reference: 16 CFR Part 429 (FTC Cooling-Off Rule), as currently in force
A homeowner signs a covered contract at the kitchen table on Friday. No holidays fall that week. What is the last day to cancel under the FTC rule?
Monday
Tuesday
Wednesday
Sunday
Show the answer
B. Tuesday
Saturday is the first business day, Monday the second and Tuesday the third, because Sundays are not business days. The buyer may cancel until midnight Tuesday. Monday forgets Saturday counts; Sunday is not a business day.
A general contractor hires a subcontractor who offers no proof of insurance. What risk does the general contractor take on?
None, because subcontractors are always fully responsible for themselves
Injury or damage claims may come back on the general contractor
Only a small fine that the insurance would pay in full
The owner automatically becomes liable instead
Show the answer
B. Injury or damage claims may come back on the general contractor
When a sub is uninsured, injured workers and affected owners often look to the general contractor, and the contractor's insurer may add premium at audit. Subcontracting does not remove the risk.
Reference: Commercial insurance practice: subcontractor risk transfer
A supplier delivers materials to a job and the contractor does not pay the bill. Who can generally record a lien on the home?
Only the homeowner who ordered and is paying for the work
Only the contractor who signed the contract with the owner
Nobody, because liens apply only to labor and not to materials
The supplier, since its materials went into the work
Show the answer
D. The supplier, since its materials went into the work
Suppliers who furnish materials used in the work generally have lien rights, subject to the notice and filing rules of the state. The idea that only labor counts is incorrect; materials qualify too.
Reference: Mechanics lien and prompt-payment statutes (general principles; the state statute named in a question controls)
During a lead-safe interior renovation, who must carry out the cleaning verification after the work is finished?
The certified renovator
Any trained worker on the crew
The property owner
A laboratory hired by the firm
Show the answer
A. The certified renovator
The certified renovator personally does the visual check and wipe-card verification. A trained worker may help clean but cannot do the verification, and a lab is only needed if a contract or law calls for dust clearance testing.
Reference: 40 CFR Part 745 Subpart E (EPA Renovation, Repair and Painting Rule, current as amended), 745.85(b) and 745.90(b)