Sample questions
A supplier delivers materials to a job and the contractor does not pay the bill. Who can generally record a lien on the home?
Only the homeowner who ordered and is paying for the work
Only the contractor who signed the contract with the owner
Nobody, because liens apply only to labor and not to materials
The supplier, since its materials went into the work
Show the answer
D. The supplier, since its materials went into the work
Suppliers who furnish materials used in the work generally have lien rights, subject to the notice and filing rules of the state. The idea that only labor counts is incorrect; materials qualify too.
Reference: Mechanics lien and prompt-payment statutes (general principles; the state statute named in a question controls)
What is the main difference between a conditional and an unconditional lien waiver?
A conditional waiver takes effect only when the payment actually clears
A conditional waiver releases rights for future work too
An unconditional waiver must be notarized and a conditional one need not be
A conditional waiver is only for suppliers
Show the answer
A. A conditional waiver takes effect only when the payment actually clears
A conditional waiver depends on the payment being received, so a bounced check does not give up lien rights. An unconditional waiver is effective as soon as it is signed. Neither covers work not yet done unless it says so, and neither is limited to suppliers.
Reference: Mechanics lien and prompt-payment statutes (general principles; the state statute named in a question controls)
A subcontractor signs an unconditional final waiver and later learns the general contractor's check bounced. What is the likely effect?
The waiver is void because the payment check later bounced
The waiver only becomes valid after a 30-day waiting period
The sub probably gave up lien rights for the amount covered
The lien rights stay in place because the payment failed
Show the answer
C. The sub probably gave up lien rights for the amount covered
An unconditional waiver is effective on signing, whether or not the money arrives. That is why a sub should sign it only after funds clear. The bounced check does not cancel it, which is the tempting wrong idea.
Reference: Mechanics lien and prompt-payment statutes (general principles; the state statute named in a question controls)