Sample questions

Who must inspect a scaffold before it is used and then at least every 7 days?

  1. Any worker who will use it
  2. The site cleaner
  3. The scaffold supervisor
  4. The signboard supplier
Show the answer

C. The scaffold supervisor

The regulation puts the duty on the scaffold supervisor, who records the result in a register. A user may spot defects and must report them, but is not the person the regulation names for the formal inspection.

Reference: WSH (Scaffolds) Regulations 2011 (S 518/2011), as currently in force

After inspecting a scaffold, the scaffold supervisor must display a notice or label saying whether it is safe for use. Where must it be displayed?

  1. Only at the main site gate entrance
  2. Only at the site office wall
  3. Only on the top lift platform
  4. At every designated access point
Show the answer

D. At every designated access point

The label goes at each designated access point so a worker sees it before climbing on. Placing it only at the gate or office would not stop someone entering the scaffold at another point.

Reference: WSH (Scaffolds) Regulations 2011 (S 518/2011), as currently in force

What is the largest vertical gap allowed between two adjacent guard-rails on a scaffold?

  1. 600 mm
  2. 450 mm
  3. 900 mm
  4. 1,000 mm
Show the answer

A. 600 mm

The vertical distance between adjacent guard-rails, and between the platform and the first rail above it, must not exceed 600 mm. A gap of 900 mm or more is big enough for a person to slip through.

Reference: WSH (Scaffolds) Regulations 2011 (S 518/2011), as currently in force