Why is the area under and around a crane lift cordoned off?
Keep people clear of load paths
To stop the crane getting dirty
To keep the lifting plan secret
To make the load lighter
Show the answer
A. Keep people clear of load paths
If a load slips or swings, anyone below or nearby can be struck. Keeping the area clear removes people from the danger zone. The other reasons have nothing to do with safety.
Reference: WSH (Operation of Cranes) Regulations 2011 (as in force)
The signalman has checked the lifting path is clear. What must he also confirm before giving the signal to lift?
That the lunch break has not started
That the engineer is on the ground floor
That the load has been painted
That the load is rigged properly
Show the answer
D. That the load is rigged properly
The signalman must confirm with the rigger that the load is properly rigged before signalling. A clear path alone does not show the slings are correct.
Reference: WSH (Operation of Cranes) Regulations 2011 (as in force)
A crane's overload alarm keeps sounding on a lift that must be finished today. What should the crew do?
Disconnect the alarm and finish quickly
Ask the signalman to ignore it
Stop, re-check; never bypass it
Lift faster so the alarm stops sooner
Show the answer
C. Stop, re-check; never bypass it
Limiting and safety devices must never be bypassed or overridden. An overload alarm means the lift is beyond what was planned; re-check the load weight and radius or use a bigger crane.
Reference: WSH (Operation of Cranes) Regulations 2011 (as in force); WSH Council rigging guidance