10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.
Sample questions
In a risk assessment, how is the level of risk usually worked out?
By combining how likely harm is with how severe it would be
By counting how many workers are on the job
By checking only how severe the injury could be
By the cost of the equipment used
Show the answer
A. By combining how likely harm is with how severe it would be
Risk rates both likelihood and severity. Severity alone is the tempting choice, but a severe harm that is very unlikely can be lower risk than a likely moderate one.
Reference: Workplace Safety and Health (Risk Management) Regulations 2006
A crew replaces a solvent with a safer product that does the same job. Which type of control is this?
Elimination
Administrative control
Personal protective equipment
Substitution
Show the answer
D. Substitution
Swapping a hazardous material for a less hazardous one is substitution. Elimination would mean not using any solvent at all.
Reference: Workplace Safety and Health (Risk Management) Regulations 2006
An injury leaves a worker on medical leave for more than three days. Within how many days of the incident must the employer report it to MOM?
Answer in days.
Show the answer
10 days
The reporting deadline is 10 days.
Reference: Workplace Safety and Health (Incident Reporting) Regulations 2006