In Victoria, a builder's direct cost is $80,000 and the builder adds a 15% markup on cost. What is the price before GST, in dollars?
Answer in $.
Show the answer
92000 $
Markup = 0.15 x 80,000 = 12,000. Price = 80,000 + 12,000 = 92,000.
Reference: Standard construction estimating arithmetic
In Queensland, after a notifiable incident, what must the person in control of the site do about the scene?
- Preserve scene until inspector arrives or directs
- Clean up straight away to avoid further risk, removing any evidence of the cause
- Move all plant and equipment involved to a depot so it can be examined later
- Photograph the site and then resume work
Show the answer
A. Preserve scene until inspector arrives or directs
The site must be preserved, with limited exceptions such as helping a person or making the site safe. Cleaning up or resuming work destroys evidence.
Reference: Work Health and Safety Act 2011 (Qld), s 39
In Queensland, from what project cost level must a principal contractor prepare a WHS management plan for a construction project?
- $50,000 or more
- $250,000 or more
- $100,000 or more
- $1,000,000 or more
Show the answer
B. $250,000 or more
The plan is required where the construction work costs $250,000 or more. The other figures are not the threshold.
Reference: Work Health and Safety Regulation 2011 (Qld), Ch 6 (construction work, WHS management plan)