TradeExamPro

Au security of payment practice questions

35 questions from the Australian builder licence (VIC, QLD) practice test.

Start practising

Au security of payment practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Sample questions

In Victoria, a subcontract says the subcontractor is paid 7 days after the head contractor receives payment from the owner. What is the effect of that clause for payment for the work under the Building and Construction Industry Security of Payment Act 2002?

  1. It is binding because both parties signed it
  2. It has no effect for payment for the work
  3. It is binding if the owner is named in the subcontract
  4. It applies only to claims after practical completion
Show the answer

B. It has no effect for payment for the work

A pay when paid provision has no effect for money owing for construction work or related goods and services. Having both parties sign it does not help, because the Act cannot be contracted out of.

Reference: Building and Construction Industry Security of Payment Act 2002 (Vic), s 13, version in force from 24 June 2026

In Queensland, a progress claim is given and the contract says nothing about when progress payments fall due. When does the payment become payable under the Building Industry Fairness (Security of Payment) Act 2017?

  1. 15 business days after the claim is made
  2. 20 business days after the claim is made
  3. 10 business days after the claim is made
  4. 30 days after the claim is made
Show the answer

C. 10 business days after the claim is made

Section 73(1)(b) sets the default due date at 10 business days after the payment claim is made. Fifteen business days is the time for the payment schedule, a different step.

Reference: Building Industry Fairness (Security of Payment) Act 2017 (Qld), s 73(1)(b), current as at 28 April 2026

A Queensland head contractor does not give a payment schedule in time and does not pay. Under the Building Industry Fairness (Security of Payment) Act 2017, what is the head contractor liable to pay on the due date?

  1. Only the amount it believes is fair
  2. The amount paid on the last claim
  3. Nothing until an adjudicator decides the claim
  4. The full amount claimed in the payment claim
Show the answer

D. The full amount claimed in the payment claim

Section 77 makes a respondent that fails to give a schedule liable for the whole claimed amount on the due date. The respondent cannot wait for adjudication and cannot argue a lower value later.

Reference: Building Industry Fairness (Security of Payment) Act 2017 (Qld), s 77, current as at 28 April 2026

Other topics