TradeExamPro

Au permits ncc practice questions

35 questions from the Australian builder licence (VIC, QLD) practice test.

Start practising

Au permits ncc practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Sample questions

For a new Class 1a house on a concrete slab in Queensland, which set of mandatory inspection stages normally applies?

  1. Footing, frame and handover only
  2. Footing, slab, frame and final
  3. Excavation, plumbing, roof and handover
  4. Slab and final only
Show the answer

B. Footing, slab, frame and final

For houses and sheds on a slab, the Queensland stages are footing, slab, frame and final. The shortened lists leave out stages where the work becomes hidden, which is why those stages exist.

Reference: Building Act 1975 (Qld), inspection stages for Class 1 and 10 buildings (Building Regulation)

In Victoria, who decides which mandatory notification stages apply to a particular building permit?

  1. The builder, in the tender document or quote
  2. The local council's planning department
  3. The relevant building surveyor, who lists them on the permit
  4. The owner, in the domestic building contract
Show the answer

C. The relevant building surveyor, who lists them on the permit

The relevant building surveyor decides and records the mandatory notification stages, such as footings, slab, frame and final, on the building permit. The builder then must give notice at each stage. The builder, owner and planning department do not set them.

Reference: Building Act 1993 (Vic), mandatory notification stages (Part 4) and Building Regulations 2018 (Vic)

A Victorian builder has finished a new detached house (Class 1a) and the final inspection has been done. What does the relevant building surveyor issue?

  1. A building order issued after the inspection
  2. An occupancy permit issued for the new house
  3. A planning permit issued by the local council
  4. A certificate of final inspection
Show the answer

D. A certificate of final inspection

For Class 1 and Class 10 buildings the relevant building surveyor issues a certificate of final inspection. An occupancy permit is for other classes such as apartments and offices. A building order is an enforcement tool, and a planning permit is issued before building starts.

Reference: Building Act 1993 (Vic), certificate of final inspection (Part 4)

Other topics