A contractor signs a home improvement contract for $6,500. What is the most the contractor may ask for as a down payment?
$1,000
$1,300
$650
$325
Show the answer
C. $650
The down payment is limited to the lesser of 10 percent of the contract price or $1,000. Ten percent of $6,500 is $650, which is less than $1,000. The $1,000 figure applies only when 10 percent would be more than $1,000.
Reference: California B&P Code 7159 and 7159.5; CSLB Law and Reference Book (2026 edition)
An owner signs a $12,000 home improvement contract. The contractor asks for a $1,200 down payment, which is 10 percent. Is that allowed?
Yes, 10 percent is always the limit
Yes, if the owner agrees in writing
No, the limit is 5 percent of the price
No, the limit is $1,000
Show the answer
D. No, the limit is $1,000
The cap is the lesser of 10 percent or $1,000. Ten percent here is $1,200, so the $1,000 limit controls. The owner's agreement does not raise the cap.
Reference: California B&P Code 7159 and 7159.5; CSLB Law and Reference Book (2026 edition)
A home improvement contract's payment schedule calls for a large payment before any work is done, well above the down payment limit. What is the problem?
Payments cannot exceed work done or materials delivered
Payment schedules are not allowed in home improvement contracts
Only the owner may decide when payments are due
Payments are allowed as long as the contractor posts a bond
Show the answer
A. Payments cannot exceed work done or materials delivered
A progress payment schedule is allowed and must be listed in the contract, but a contractor may not collect payment for work not performed or materials not delivered. A bond does not change that, and the schedule is written into the contract by both sides.
Reference: California B&P Code 7159 and 7159.5; CSLB Law and Reference Book (2026 edition)