A subcontractor first delivers materials to a private job on June 1 but serves its preliminary notice on June 30. Work from which date forward is protected by the notice?

  1. From June 1, the first delivery
  2. Only work after June 30
  3. None; late notice voids all rights
  4. From June 10, twenty days before the notice
Show the answer

D. From June 10, twenty days before the notice

A late notice still protects work furnished beginning 20 days before the notice was given. June 30 minus 20 days is June 10. It does not reach back to June 1, and it does not wipe out every right.

Reference: California Civil Code 8200-8216 (preliminary notice)

The owner of a private project records a notice of completion. A direct contractor who was not fully paid has how long after that recording to record a claim of lien?

  1. 30 days
  2. 45 days
  3. 60 days
  4. 90 days
Show the answer

C. 60 days

When a valid notice of completion is recorded, a direct contractor has 60 days from the recording. Thirty days is the shorter period that applies to subcontractors and other claimants; 90 days applies when no notice is recorded.

Reference: California Civil Code 8412

An owner records a notice of completion. A subcontractor who was not paid has how long after the recording to record its claim of lien?

  1. 30 days
  2. 45 days
  3. 60 days
  4. 90 days
Show the answer

A. 30 days

Claimants other than the direct contractor have 30 days after a notice of completion is recorded. The 60-day period belongs to the direct contractor, so a subcontractor who assumes 60 days can lose the lien.

Reference: California Civil Code 8414