Sample questions

Workers must step into a 6-foot-deep pool excavation cut in loose, sandy soil. What does OSHA require?

  1. Nothing, because pool digs are exempt from the rule
  2. A protective system such as sloping, shoring or a shield
  3. Only a warning barricade around the top
  4. Only a ladder at one end
Show the answer

B. A protective system such as sloping, shoring or a shield

Excavations 5 feet or deeper need a protective system unless they are cut in stable rock, and loose sand is far from that. A barricade and a ladder are needed too but do not stop a cave-in.

Reference: 29 CFR 1926.652(a)(1) (protective systems for excavations 5 feet or deeper)

In a trench 4 feet or more deep, how close must workers be to a way out such as a ladder or ramp?

  1. Within 100 feet of lateral travel
  2. Within 50 feet of lateral travel
  3. Within 25 feet of lateral travel
  4. Within 10 feet of lateral travel
Show the answer

C. Within 25 feet of lateral travel

OSHA requires a stairway, ladder, ramp or other safe way out so that no worker has more than 25 feet of lateral travel to reach it. Longer distances delay escape in a cave-in.

Reference: 29 CFR 1926.651(c)(2)

What is the nominal diameter of a #4 reinforcing bar?

  1. 1/4 inch
  2. 3/8 inch
  3. 4 inches
  4. 1/2 inch
Show the answer

D. 1/2 inch

Bar sizes are counted in eighths of an inch, so #4 is 4/8 inch, or 1/2 inch. A #3 is 3/8 inch, and the number is never the diameter in whole inches.

Reference: ASTM A615 reinforcing bar designations; concrete reinforcement practice