UK Site Management Safety and NEBOSH Construction Practice Test
Practice questions on UK construction health and safety law and management: CDM 2015, working at height, excavation and lifting, health hazards, site management and risk management.
Prices are in US dollars, plus tax where it applies. Stripe, our payment processor and the seller of record, adds tax at checkout.
All sales are final. If something is really wrong, such as a duplicate charge or a purchase that does not unlock what you bought, write to support@tradeexampro.com and we will put it right.
One-time payment. Nothing renews.
You have an exam ticket for this practice test. Start the mock exam to use it.
28 working days, never more than 15 workers at once, 300 person days in total
45 working days, 25 workers on site at once at one point, 600 person days in total
40 working days, never more than 12 workers at once, 380 person days in total
20 working days, never more than 18 workers at once, 340 person days in total
Show the answer
B. 45 working days, 25 workers on site at once at one point, 600 person days in total
A project is notifiable if it lasts more than 30 working days with more than 20 workers on site at once at some point, or if it exceeds 500 person days. Only the first project meets a test (over 30 days with 25 workers at once, and also over 500 person days). The others last 30 days or fewer, never pass 20 workers, or stay under 500 person days.
Reference: CDM 2015 reg 6
A tradesperson has a daily noise exposure of 82 dB(A) with no hearing protection. What must the employer do about hearing protection?
Make wearing hearing protection compulsory in the work area
Make protectors available to anyone who asks
Do nothing, because the exposure is below every action value
Provide ear plugs only when noise peaks exceed 140 dB(C)
Show the answer
B. Make protectors available to anyone who asks
82 dB(A) is above the lower exposure action value of 80 dB(A) but below the upper value of 85 dB(A), so protectors must be offered to those who ask. Wearing them becomes mandatory only at the upper value.
Reference: Control of Noise at Work Regulations 2005, reg 7
A mobile crane is used to lift materials only (not people) and has no special examination scheme. What is the longest normal interval between thorough examinations?
3 months
12 months
6 months
24 months
Show the answer
B. 12 months
General lifting equipment needs a thorough examination at least every 12 months. The 6-month interval applies to equipment that lifts people and to lifting accessories.
Reference: LOLER 1998, reg 9
A site agent deducts £8 from each labourer's wages to cover the hard hats they have to wear on site. Which section of the 1974 Act does this breach?
Section 9: no charge for anything provided for health and safety
Section 3: the duty owed to people who are not employees
Section 8: no interfering with or misusing safety equipment on site
Section 37: offences by company directors
Show the answer
A. Section 9: no charge for anything provided for health and safety
Section 9 stops an employer charging employees for anything done or provided because of a specific legal requirement, which includes PPE the law requires. Section 8 is about misuse of equipment, not charging.
Reference: Health and Safety at Work etc. Act 1974, s9
In the HSE five steps to risk assessment, what comes straight after identifying the hazards?
Decide who might be harmed and how
Record the findings
Review the assessment
Choose the personal protective equipment
Show the answer
A. Decide who might be harmed and how
After spotting the hazards you decide who could be harmed and how. Recording and review come later, and PPE is chosen only when other controls cannot do enough.
Reference: HSE Five steps to risk assessment (INDG163)