TradeExamPro

Uk height excavation lifting practice questions

36 questions from the UK site safety (SMSTS, SSSTS, NEBOSH) practice test.

Start practising

Uk height excavation lifting practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Sample questions

A mobile crane is used to lift materials only (not people) and has no special examination scheme. What is the longest normal interval between thorough examinations?

  1. 3 months
  2. 12 months
  3. 6 months
  4. 24 months
Show the answer

B. 12 months

General lifting equipment needs a thorough examination at least every 12 months. The 6-month interval applies to equipment that lifts people and to lifting accessories.

Reference: LOLER 1998, reg 9

When must a trench that needs support be inspected by a competent person?

  1. Once, when the trench is first dug and before anyone enters it
  2. Once a week, on the same day as the scaffold inspection
  3. At the start of each shift, and after any event that could affect stability
  4. Only after heavy rain or a fall of material has been reported
Show the answer

C. At the start of each shift, and after any event that could affect stability

Supported excavations must be inspected before work starts each shift and after events such as falls of material. One check at the start of the job or after rain alone would miss changes in between.

Reference: CDM 2015 (SI 2015/51), reg 22(4) and reg 24

What is the minimum height of the top guard rail on a working scaffold platform?

  1. 600 mm
  2. 800 mm
  3. 1100 mm
  4. 950 mm above the platform
Show the answer

D. 950 mm above the platform

Schedule 2 sets the top guard rail at no lower than 950 mm. Lower rails leave too little protection against falling over the edge.

Reference: Work at Height Regulations 2005, Schedule 2