TradeExamPro

Uk cdm 2015 practice questions

36 questions from the UK site safety (SMSTS, SSSTS, NEBOSH) practice test.

Start practising

Uk cdm 2015 practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Sample questions

Which project must be notified to the HSE?

  1. 28 working days, never more than 15 workers at once, 300 person days in total
  2. 45 working days, 25 workers on site at once at one point, 600 person days in total
  3. 40 working days, never more than 12 workers at once, 380 person days in total
  4. 20 working days, never more than 18 workers at once, 340 person days in total
Show the answer

B. 45 working days, 25 workers on site at once at one point, 600 person days in total

A project is notifiable if it lasts more than 30 working days with more than 20 workers on site at once at some point, or if it exceeds 500 person days. Only the first project meets a test (over 30 days with 25 workers at once, and also over 500 person days). The others last 30 days or fewer, never pass 20 workers, or stay under 500 person days.

Reference: CDM 2015 reg 6

A homeowner has an extension built by a single builder. Where do the normal client duties go?

  1. They pass to the contractor, or to the principal contractor if there is more than one contractor
  2. They pass to the local building control officer
  3. They stay with the homeowner and cannot be passed on
  4. They disappear because CDM does not apply to homes
Show the answer

A. They pass to the contractor, or to the principal contractor if there is more than one contractor

For a domestic client, the client duties pass to the contractor (or the principal contractor where there is more than one), unless there is a written agreement for the principal designer to take them on. CDM still applies to domestic work, and the homeowner is not left holding everything.

Reference: CDM 2015 reg 7; HSE L153 Managing health and safety in construction (CDM 2015 guidance)

Who must make sure pre-construction information is provided to every designer and contractor appointed or being considered for a project?

  1. The principal contractor
  2. The HSE
  3. The client
  4. Each subcontractor
Show the answer

C. The client

The client holds this duty and does it as soon as practicable. The principal designer helps the client gather and prepare it, but the duty to provide it stays with the client.

Reference: CDM 2015 reg 4; HSE L153 Managing health and safety in construction (CDM 2015 guidance)

Other topics