Gold Seal Construction Management Practice Test

Practice questions on Canadian construction management: contracts, estimating and bidding, planning and scheduling, safety management, and business risk, for people preparing for Gold Seal style management topics.

170 questions · 5 topics · start free, no sign-up

Start practising

Mixed practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Timed mock exam

50 questions in 60 minutes, drawn from every topic. No answers shown until the end, then a score, your weakest topics and a review of what you missed.

Practise by topic

Sample questions

Which party is protected by a labour and material payment bond?

  1. The owner's lender only
  2. The general contractor's head office staff
  3. Subcontractors and suppliers who are not paid
  4. The project designer
Show the answer

C. Subcontractors and suppliers who are not paid

The payment bond lets unpaid subcontractors and suppliers claim against the surety. It is not about completion of the work, which is the performance bond's role.

Reference: Construction management practice: surety bonding

On a stipulated price job the owner orders extra work and wants it started now, but the price has not been agreed. Which document is normally used?

  1. A change order
  2. A change directive
  3. A request for information
  4. A certificate of substantial performance
Show the answer

B. A change directive

A change directive is a written instruction to proceed before the price is settled, with the value worked out afterward. A change order records an agreed change in price and time, so it cannot be used when nothing is agreed yet.

Reference: CCDC 2 stipulated price contract, Part 6 Changes in the Work

Why does an estimator add a waste or overage allowance to a material takeoff?

  1. Suppliers only deliver in round numbers that never match the drawings
  2. Cutting, breakage and fit losses mean more must be bought than the net quantity
  3. It raises the contractor's profit percentage on the material it buys
  4. The drawings always understate the quantities by a fixed set amount
Show the answer

B. Cutting, breakage and fit losses mean more must be bought than the net quantity

Net takeoff quantities are what remain in the finished work. Offcuts, damage and layout losses are real costs, so a waste factor is added to the quantity to buy. It is a cost, not profit.

Reference: Construction estimating practice: quantity takeoff and pricing

In a finish-to-start relationship, what is the rule?

  1. Both activities must start on the same day, whatever their durations are
  2. The successor cannot start until the predecessor finishes
  3. The successor cannot finish until the predecessor starts
  4. The successor must finish when the predecessor finishes
Show the answer

B. The successor cannot start until the predecessor finishes

Finish-to-start is the usual logic link, such as pouring a slab before framing. The option about finishing after a start describes a start-to-finish link, which is rare.

Reference: CPM scheduling practice: critical path, float and network logic

A crew starts a new task that has not been done on this project before. Which step best belongs before the work starts?

  1. Hold the safety meeting after the first shift
  2. Assess hazards and brief crew on controls
  3. Wait to see whether an incident happens
  4. Ask workers to bring their own equipment
Show the answer

B. Assess hazards and brief crew on controls

Hazards need to be identified and controlled before exposure begins, and the crew must hear what the controls are. Doing it after the first shift or after an incident is reactive and leaves the crew exposed.

Reference: Hazard assessment and control process; Ontario OHSA, R.S.O. 1990, c. O.1 (current consolidation), s. 25(2)(a) and (h)