In a finish-to-start relationship, what is the rule?
Both activities must start on the same day, whatever their durations are
The successor cannot start until the predecessor finishes
The successor cannot finish until the predecessor starts
The successor must finish when the predecessor finishes
Show the answer
B. The successor cannot start until the predecessor finishes
Finish-to-start is the usual logic link, such as pouring a slab before framing. The option about finishing after a start describes a start-to-finish link, which is rare.
Reference: CPM scheduling practice: critical path, float and network logic
Negative float on a schedule update means what?
The job is ahead of schedule
An activity was entered with a negative duration during the schedule update
The job is forecast to finish after the required date
The budget is underspent
Show the answer
C. The job is forecast to finish after the required date
Negative float shows the logic and durations push the finish past its target. It is not ahead of schedule, which is what a positive number would suggest.
Reference: CPM scheduling practice: critical path, float and network logic
What is the aim of resource leveling in a schedule?
Paying all crews the same wage rate
Adding overtime to hold every finish date, whatever the cost to the job
Deleting float from non-critical tasks
Shifting work so crew demand stays within what is available
Show the answer
D. Shifting work so crew demand stays within what is available
Leveling moves activities to smooth out peaks in labour or equipment use. Overtime is a different tool that adds cost and does not smooth demand.
Reference: Resource planning and leveling in project scheduling