Sample questions
On a stipulated price job the owner orders extra work and wants it started now, but the price has not been agreed. Which document is normally used?
A change order
A change directive
A request for information
A certificate of substantial performance
Show the answer
B. A change directive
A change directive is a written instruction to proceed before the price is settled, with the value worked out afterward. A change order records an agreed change in price and time, so it cannot be used when nothing is agreed yet.
Reference: CCDC 2 stipulated price contract, Part 6 Changes in the Work
Under Ontario's Construction Act, what percentage of the price of services or materials must a payer generally hold back from each payment?
5%, as most trades expect
15%, until substantial performance
10%
20%, on the first payment only
Show the answer
C. 10%
The statutory holdback is 10 percent of the value of the work and materials, retained so that lien claimants have a fund to recover from. Other percentages are not the Ontario rule.
Reference: Construction Act, R.S.O. 1990, c. C.30 (Ontario, current consolidation, post-2018 regime), holdback provisions
What is a construction lien?
A court order freezing the contractor's bank accounts
A fine charged to the contractor for late completion
A refund demand that an owner sends to a contractor
A claim registered on title for unpaid work or materials
Show the answer
D. A claim registered on title for unpaid work or materials
A lien gives an unpaid supplier or trade a security interest in the improved property, which is why owners watch the registry. It is not a personal fine or a bank freeze.
Reference: Construction Act, R.S.O. 1990, c. C.30 (Ontario, current consolidation, post-2018 regime), lien provisions