TradeExamPro

Gs estimating bidding practice questions

35 questions from the Gold Seal certification (Canada) practice test.

Start practising

Gs estimating bidding practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Sample questions

Why does an estimator add a waste or overage allowance to a material takeoff?

  1. Suppliers only deliver in round numbers that never match the drawings
  2. Cutting, breakage and fit losses mean more must be bought than the net quantity
  3. It raises the contractor's profit percentage on the material it buys
  4. The drawings always understate the quantities by a fixed set amount
Show the answer

B. Cutting, breakage and fit losses mean more must be bought than the net quantity

Net takeoff quantities are what remain in the finished work. Offcuts, damage and layout losses are real costs, so a waste factor is added to the quantity to buy. It is a cost, not profit.

Reference: Construction estimating practice: quantity takeoff and pricing

Which cost belongs in the project overhead (general conditions) of an estimate?

  1. The drywall boards installed in a corridor
  2. The concrete poured in a slab
  3. Site superintendent and office trailer
  4. The paint applied to a ceiling
Show the answer

C. Site superintendent and office trailer

Site supervision, trailers and temporary services support the whole job and are carried as project overhead. Boards, concrete and paint are direct costs of specific work items.

Reference: Construction estimating practice: markup, overhead and profit

What does a bid bond give the owner?

  1. Assurance that the finished work will be free of defects for one full year
  2. Payment for all subtrades and suppliers on the project if the contractor fails to pay
  3. Protection for the bidder against a late payment by the owner after award
  4. That the bidder will sign if awarded, or the surety pays the owner up to the bond amount
Show the answer

D. That the bidder will sign if awarded, or the surety pays the owner up to the bond amount

A bid bond secures the bid itself: if the low bidder refuses to enter the contract, the owner can claim against the bond. Defect and payment protection come from other bonds or provisions.

Reference: Canadian tendering practice: instructions to bidders and bid documents

Other topics