Why does an estimator add a waste or overage allowance to a material takeoff?
Suppliers only deliver in round numbers that never match the drawings
Cutting, breakage and fit losses mean more must be bought than the net quantity
It raises the contractor's profit percentage on the material it buys
The drawings always understate the quantities by a fixed set amount
Show the answer
B. Cutting, breakage and fit losses mean more must be bought than the net quantity
Net takeoff quantities are what remain in the finished work. Offcuts, damage and layout losses are real costs, so a waste factor is added to the quantity to buy. It is a cost, not profit.
Reference: Construction estimating practice: quantity takeoff and pricing
Which cost belongs in the project overhead (general conditions) of an estimate?
The drywall boards installed in a corridor
The concrete poured in a slab
Site superintendent and office trailer
The paint applied to a ceiling
Show the answer
C. Site superintendent and office trailer
Site supervision, trailers and temporary services support the whole job and are carried as project overhead. Boards, concrete and paint are direct costs of specific work items.
Reference: Construction estimating practice: markup, overhead and profit
What does a bid bond give the owner?
Assurance that the finished work will be free of defects for one full year
Payment for all subtrades and suppliers on the project if the contractor fails to pay
Protection for the bidder against a late payment by the owner after award
That the bidder will sign if awarded, or the surety pays the owner up to the bond amount
Show the answer
D. That the bidder will sign if awarded, or the surety pays the owner up to the bond amount
A bid bond secures the bid itself: if the low bidder refuses to enter the contract, the owner can claim against the bond. Defect and payment protection come from other bonds or provisions.
Reference: Canadian tendering practice: instructions to bidders and bid documents