Which party is protected by a labour and material payment bond?
The owner's lender only
The general contractor's head office staff
Subcontractors and suppliers who are not paid
The project designer
Show the answer
C. Subcontractors and suppliers who are not paid
The payment bond lets unpaid subcontractors and suppliers claim against the surety. It is not about completion of the work, which is the performance bond's role.
Reference: Construction management practice: surety bonding
Why would a general contractor require subcontractors to name it as an additional insured on their liability policies?
To cut the subcontractor's premium
To claim under the sub's cover for related losses
To avoid writing a subcontract agreement
To release the subcontractor from all liability
Show the answer
B. To claim under the sub's cover for related losses
Additional insured status gives the general contractor access to the sub's liability cover for claims arising from the sub's work. It does not lower premiums or replace the written subcontract.
Reference: Construction management practice: risk management
A fire causes $48,000 of covered damage. The policy has a $5,000 deductible. How much does the insurer pay, in dollars?
Answer in dollars.
Show the answer
43000 dollars
Insurer pays loss minus deductible: 48,000 - 5,000 = 43,000.
Reference: Construction management practice: insurance for contractors