Practice questions on quantity takeoff, unit costs, labor and equipment pricing, overhead, profit, contingency, bidding and cost control for construction estimators.

175 questions · 5 topics · start free, no sign-up

Start practising

Mixed practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Timed mock exam

50 questions in 60 minutes, drawn from every topic. No answers shown until the end, then a score, your weakest topics and a review of what you missed.

Practise by topic

Sample questions

On a project the earned value (budgeted cost of work performed) is $240,000 and the actual cost to date is $300,000. What is the cost performance index (CPI)?

Answer in ratio.

Show the answer

0.8 ratio

CPI = earned value / actual cost = 240,000 / 300,000 = 0.80. A value below 1.0 means the work is costing more than budgeted.

Reference: PMI, Practice Standard for Earned Value Management, 3rd ed. (2019); cost performance index (CPI = EV / AC)

Direct cost of a job is $800,000. Add overhead of 10% of direct cost, then add profit of 8% on the sum of direct cost and overhead. What is the bid price in dollars?

Answer in dollars.

Show the answer

950400 dollars

800,000 x 1.10 = 880,000 with overhead. 880,000 x 1.08 = 950,400 with profit.

Reference: Universal estimating practice (AACE/ASPE general estimating principles); no edition-specific code

A slab is 50 ft long, 24 ft wide and 4 in. thick. How many cubic yards of concrete are needed before waste?

Answer in cubic yards.

Show the answer

14.81 cubic yards

4 in. = 0.3333 ft. 50 x 24 x 0.3333 = 400 cu ft. 400 / 27 = 14.81 cu yd.

Reference: Estimating practice: concrete takeoff

Under CSI MasterFormat division titles, which division covers Heating, Ventilating and Air Conditioning?

  1. Division 21
  2. Division 22
  3. Division 26
  4. Division 23
Show the answer

D. Division 23

HVAC is Division 23. Division 22 is Plumbing, Division 21 is Fire Suppression and Division 26 is Electrical.

Reference: CSI MasterFormat division titles (general practice, no edition-specific numbering)

A carpenter earns a base wage of $30.00 per hour. Labor burden is 35% of base wage. What is the burdened hourly rate?

Answer in $/hour.

Show the answer

40.5 $/hour

30.00 x 0.35 = 10.50 burden; 30.00 + 10.50 = 40.50.

Reference: Construction estimating practice: crew, labor and equipment pricing (general estimating method, no code edition)