Practice questions on quantity takeoff, unit costs, labor and equipment pricing, overhead, profit, contingency, bidding and cost control for construction estimators.
Prices are in US dollars, plus tax where it applies. Stripe, our payment processor and the seller of record, adds tax at checkout.
All sales are final. If something is really wrong, such as a duplicate charge or a purchase that does not unlock what you bought, write to support@tradeexampro.com and we will put it right.
One-time payment. Nothing renews.
You have an exam ticket for this practice test. Start the mock exam to use it.
On a project the earned value (budgeted cost of work performed) is $240,000 and the actual cost to date is $300,000. What is the cost performance index (CPI)?
Answer in ratio.
Show the answer
0.8 ratio
CPI = earned value / actual cost = 240,000 / 300,000 = 0.80. A value below 1.0 means the work is costing more than budgeted.
Reference: PMI, Practice Standard for Earned Value Management, 3rd ed. (2019); cost performance index (CPI = EV / AC)
Direct cost of a job is $800,000. Add overhead of 10% of direct cost, then add profit of 8% on the sum of direct cost and overhead. What is the bid price in dollars?
Answer in dollars.
Show the answer
950400 dollars
800,000 x 1.10 = 880,000 with overhead. 880,000 x 1.08 = 950,400 with profit.
Reference: Universal estimating practice (AACE/ASPE general estimating principles); no edition-specific code
A slab is 50 ft long, 24 ft wide and 4 in. thick. How many cubic yards of concrete are needed before waste?
Answer in cubic yards.
Show the answer
14.81 cubic yards
4 in. = 0.3333 ft. 50 x 24 x 0.3333 = 400 cu ft. 400 / 27 = 14.81 cu yd.
Reference: Estimating practice: concrete takeoff
Under CSI MasterFormat division titles, which division covers Heating, Ventilating and Air Conditioning?
Division 21
Division 22
Division 26
Division 23
Show the answer
D. Division 23
HVAC is Division 23. Division 22 is Plumbing, Division 21 is Fire Suppression and Division 26 is Electrical.
Reference: CSI MasterFormat division titles (general practice, no edition-specific numbering)
A carpenter earns a base wage of $30.00 per hour. Labor burden is 35% of base wage. What is the burdened hourly rate?