On a project the earned value (budgeted cost of work performed) is $240,000 and the actual cost to date is $300,000. What is the cost performance index (CPI)?

Answer in ratio.

Show the answer

0.8 ratio

CPI = earned value / actual cost = 240,000 / 300,000 = 0.80. A value below 1.0 means the work is costing more than budgeted.

Reference: PMI, Practice Standard for Earned Value Management, 3rd ed. (2019); cost performance index (CPI = EV / AC)

A job has earned value of $180,000 and a planned value (budgeted cost of work scheduled) of $200,000. What is the schedule performance index (SPI)?

Answer in ratio.

Show the answer

0.9 ratio

SPI = earned value / planned value = 180,000 / 200,000 = 0.90. Below 1.0 means the job is behind schedule in terms of value of work done.

Reference: PMI, Practice Standard for Earned Value Management, 3rd ed. (2019); schedule performance index (SPI = EV / PV)

Earned value is $450,000 and actual cost to date is $495,000. What is the cost variance in dollars? Enter a negative number for an overrun.

Answer in $.

Show the answer

-45000 $

Cost variance = earned value - actual cost = 450,000 - 495,000 = -45,000. The negative sign shows the work to date cost $45,000 more than it was worth in budget.

Reference: PMI, Practice Standard for Earned Value Management, 3rd ed. (2019); cost variance (CV = EV - AC)