Under CSI MasterFormat division titles, which division covers Heating, Ventilating and Air Conditioning?
Division 21
Division 22
Division 26
Division 23
Show the answer
D. Division 23
HVAC is Division 23. Division 22 is Plumbing, Division 21 is Fire Suppression and Division 26 is Electrical.
Reference: CSI MasterFormat division titles (general practice, no edition-specific numbering)
On a cost-plus contract, who carries most of the risk of the actual cost running higher than expected?
The owner
The general contractor
The design team's insurer
The material suppliers
Show the answer
A. The owner
The owner reimburses the actual allowable cost, so overruns land on the owner. Under lump sum the contractor would carry that risk.
Reference: Construction estimating practice: estimate types and contract delivery methods (general practice, no edition-specific code)
When is a square-foot estimate most useful?
Pricing a change order for one wall
Checking a subcontractor's final quote line by line
Early budgeting from type and floor area
Ordering reinforcing steel for a slab
Show the answer
C. Early budgeting from type and floor area
Square-foot costs come from past projects and need only a building type and area, so they suit early budgets. They are too coarse for a change order or an order quantity.
Reference: Construction estimating practice: estimate types and contract delivery methods (general practice, no edition-specific code)