A slab is 50 ft long, 24 ft wide and 4 in. thick. How many cubic yards of concrete are needed before waste?
Answer in cubic yards.
Show the answer
14.81 cubic yards
4 in. = 0.3333 ft. 50 x 24 x 0.3333 = 400 cu ft. 400 / 27 = 14.81 cu yd.
Reference: Estimating practice: concrete takeoff
A room has walls 20 ft by 14 ft in plan, 9 ft high, with one door 21 sq ft and one window 15 sq ft. Drywall is 4 x 8 sheets and the waste allowance is 10% on the net wall area. How many sheets are needed (round up)?
Answer in sheets.
Show the answer
20 sheets
Perimeter = 2 x (20 + 14) = 68 ft. Gross = 68 x 9 = 612 sq ft. Net = 612 - 36 = 576 sq ft. With waste: 576 x 1.10 = 633.6 sq ft. Sheet = 32 sq ft. 633.6 / 32 = 19.8, round up to 20.
Reference: Estimating practice: drywall takeoff
A wall measures 3 in. on a drawing at 1/4 in. = 1 ft-0 in. What is its real length?
0.75 ft
12 ft
36 ft
48 ft
Show the answer
B. 12 ft
Each 1/4 in. is 1 ft, so 3 in. divided by 0.25 gives 12 ft. Multiplying by 12 or 16 instead of dividing by 0.25 produces the wrong values.