Est overhead profit bidding practice questions

35 questions from the Construction estimating (CPE) practice test.

Start practising

Est overhead profit bidding practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Sample questions

Direct cost of a job is $800,000. Add overhead of 10% of direct cost, then add profit of 8% on the sum of direct cost and overhead. What is the bid price in dollars?

Answer in dollars.

Show the answer

950400 dollars

800,000 x 1.10 = 880,000 with overhead. 880,000 x 1.08 = 950,400 with profit.

Reference: Universal estimating practice (AACE/ASPE general estimating principles); no edition-specific code

A contractor marks up cost by 25% to get the selling price. What is the gross margin as a percentage of selling price?

  1. 25%
  2. 30%
  3. 20%
  4. 15%
Show the answer

C. 20%

On cost 100 the price is 125; the 25 of markup is 25/125 = 20% of price. Margin is always lower than markup because it is divided by the larger price figure.

Reference: Universal estimating practice (AACE/ASPE general estimating principles); no edition-specific code

An estimator wants a 15% gross margin on selling price. Total cost is $340,000. What price in dollars gives that margin?

Answer in dollars.

Show the answer

400000 dollars

Cost is 85% of price (100% - 15%). Price = 340,000 / 0.85 = 400,000.

Reference: Universal estimating practice (AACE/ASPE general estimating principles); no edition-specific code