Sample questions
A hole was cut in the roof of a multi-section home during set-up. Before exterior close-up is finished, what must be done with it?
Seal it with a roofing-suitable sealant or material
Leave it open for a day so trapped moisture can escape
Cover it with plastic sheeting and tape the edges
Pack it with fiberglass insulation and cover it with felt
Show the answer
A. Seal it with a roofing-suitable sealant or material
Roof holes must be made weatherproof before close-up is complete, using material suited to the roof covering. Plastic or insulation alone does not stay watertight on a roof.
Reference: 24 CFR 3285.801(d), eCFR current as of Nov 2026
Before exterior close-up is complete, up to what gap may exist between interconnected structural elements at the mate-line, provided the other conditions are met?
1/4 inch
1 inch
2 inches
3 inches
Show the answer
B. 1 inch
A gap of up to 1 inch is tolerated before close-up if the sections touch, the gasket still seals and the gap is closed before close-up is finished. Larger gaps are not allowed.
Reference: 24 CFR 3285.802(c), eCFR current as of Nov 2026
After exterior close-up of a multi-section home is complete, how large a gap may remain between interconnected structural elements at the mate-line?
Up to 1/4 inch
Up to 1 inch if shimmed
None; no gaps are allowed
Up to 1/4 inch if filled with caulk
Show the answer
C. None; no gaps are allowed
The 1 inch allowance applies only before close-up and must be closed by the time close-up ends. Once close-up is done, no gaps are allowed, and caulk is not a structural fix.
Reference: 24 CFR 3285.802(c), eCFR current as of Nov 2026