Practice questions on people, process and business environment project management topics with construction scenarios, for learners studying project management fundamentals.
Prices are in US dollars, plus tax where it applies. Stripe, our payment processor and the seller of record, adds tax at checkout.
All sales are final. If something is really wrong, such as a duplicate charge or a purchase that does not unlock what you bought, write to support@tradeexampro.com and we will put it right.
One-time payment. Nothing renews.
You have an exam ticket for this practice test. Start the mock exam to use it.
Halfway through a facility upgrade, the owner changes its strategy and the project no longer supports its goals, though the work is on schedule. What should the project manager do?
Raise the situation with the sponsor and governance body so they can reassess whether to continue
Keep going quietly with the work because the schedule is on track and nothing else has changed and leave the sponsor and governance body out of it entirely
Cut the team size to save money without telling the sponsor or anyone else in charge
Add extra scope to the project in an attempt to make it fit the new strategy
Show the answer
A. Raise the situation with the sponsor and governance body so they can reassess whether to continue
A project exists to serve strategy, so a strategic change must go to the people who decide whether it should continue, change or stop. Being on schedule does not justify delivering something the organization no longer wants.
Reference: PMI PMP Examination Content Outline effective 9 July 2026, Business Environment domain
On a design-bid-build job, the drawings contain a defect the contractor could not have found by reasonable review. Who generally carries the risk of that design defect as between owner and contractor?
The owner, who supplies the plans and specifications
The contractor, because it signed the construction contract
The lowest bidding subcontractor on the affected trade
Both parties equally, under every kind of construction contract
Show the answer
A. The owner, who supplies the plans and specifications
Under the widely applied US rule, the owner impliedly warrants that plans it furnishes are adequate if followed. The contractor still must follow contract notice and review duties, but it does not usually own the design risk.
Reference: US implied warranty of plans and specifications (Spearin doctrine); contract documents govern
A superintendent says the crew only works hard when watched and avoids responsibility. A manager who believes this treats workers according to which theory?
McGregor Theory Y
McGregor Theory X
Herzberg hygiene theory
Maslow self-actualisation
Show the answer
B. McGregor Theory X
Theory X assumes people dislike work and need close control. Theory Y assumes people seek responsibility, the opposite of this belief.
Reference: McGregor, The Human Side of Enterprise (Theory X and Theory Y)
Which description best fits the critical path of a project network?
The longest path through the network, which sets the shortest possible project duration
The path with the most expensive activities in the whole network
The path with the most float available to its activities
The path that uses the most labor and equipment resources
Show the answer
A. The longest path through the network, which sets the shortest possible project duration
The critical path is the longest-duration path, and any delay on it delays the finish. Cost, float and resource use do not define it; critical activities normally have the least float.
Reference: Project management fundamentals: critical path method and schedule compression
A risk has a 30 percent probability and a cost impact of $80,000. What is its expected monetary value?
Answer in $.
Show the answer
24000 $
EMV = probability x impact = 0.30 x 80,000 = 24,000.
Reference: PMI Standard for Risk Management in Portfolios, Programs, and Projects (2019 edition), risk responses and analysis