A risk has a 30 percent probability and a cost impact of $80,000. What is its expected monetary value?
Answer in $.
Show the answer
24000 $
EMV = probability x impact = 0.30 x 80,000 = 24,000.
Reference: PMI Standard for Risk Management in Portfolios, Programs, and Projects (2019 edition), risk responses and analysis
Which contract type places most of the cost risk on the buyer?
Firm fixed-price
Fixed-price with economic price adjustment
Lump-sum design-bid-build
Cost-plus-fixed-fee
Show the answer
D. Cost-plus-fixed-fee
The buyer reimburses actual cost, so overruns land on the buyer. The fixed-price types leave cost growth mainly with the seller.
Reference: FAR 16.3 (cost-reimbursement contracts) and 16.202 (firm-fixed-price)
What is the main purpose of a probability and impact matrix?
To rank identified risks so the team knows which to analyze and respond to first
To calculate the dollar value of the project contingency
To show which tasks sit on the critical path
To record who approved each risk response
Show the answer
A. To rank identified risks so the team knows which to analyze and respond to first
The matrix is a qualitative tool that scores each risk by how likely it is and how much it matters. It does not produce dollar figures; that is quantitative work.