10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.
Sample questions
Which description best fits the critical path of a project network?
The longest path through the network, which sets the shortest possible project duration
The path with the most expensive activities in the whole network
The path with the most float available to its activities
The path that uses the most labor and equipment resources
Show the answer
A. The longest path through the network, which sets the shortest possible project duration
The critical path is the longest-duration path, and any delay on it delays the finish. Cost, float and resource use do not define it; critical activities normally have the least float.
Reference: Project management fundamentals: critical path method and schedule compression
A contractor starts framing on the second floor before the first-floor framing is finished, accepting more rework risk to save time. What is this technique?
Crashing
Resource leveling
Value engineering
Fast tracking
Show the answer
D. Fast tracking
Fast tracking does activities in parallel that were planned in sequence, which saves time but raises risk. Crashing adds resources and cost to the same sequence instead.
Reference: Project management fundamentals: critical path method and schedule compression
The owner wants the building finished two weeks sooner, and the PM approves overtime and an added crew on critical tasks. Which technique is this?
Fast tracking
Rolling wave planning
Crashing
Scope validation
Show the answer
C. Crashing
Crashing adds resources, such as overtime or crews, to shorten critical-path activities, usually raising cost. Fast tracking changes the logic and leaves resources the same.
Reference: Project management fundamentals: critical path method and schedule compression