Which description best fits the critical path of a project network?

  1. The longest path through the network, which sets the shortest possible project duration
  2. The path with the most expensive activities in the whole network
  3. The path with the most float available to its activities
  4. The path that uses the most labor and equipment resources
Show the answer

A. The longest path through the network, which sets the shortest possible project duration

The critical path is the longest-duration path, and any delay on it delays the finish. Cost, float and resource use do not define it; critical activities normally have the least float.

Reference: Project management fundamentals: critical path method and schedule compression

A contractor starts framing on the second floor before the first-floor framing is finished, accepting more rework risk to save time. What is this technique?

  1. Crashing
  2. Resource leveling
  3. Value engineering
  4. Fast tracking
Show the answer

D. Fast tracking

Fast tracking does activities in parallel that were planned in sequence, which saves time but raises risk. Crashing adds resources and cost to the same sequence instead.

Reference: Project management fundamentals: critical path method and schedule compression

The owner wants the building finished two weeks sooner, and the PM approves overtime and an added crew on critical tasks. Which technique is this?

  1. Fast tracking
  2. Rolling wave planning
  3. Crashing
  4. Scope validation
Show the answer

C. Crashing

Crashing adds resources, such as overtime or crews, to shorten critical-path activities, usually raising cost. Fast tracking changes the logic and leaves resources the same.

Reference: Project management fundamentals: critical path method and schedule compression