Sample questions
Halfway through a facility upgrade, the owner changes its strategy and the project no longer supports its goals, though the work is on schedule. What should the project manager do?
Raise the situation with the sponsor and governance body so they can reassess whether to continue
Keep going quietly with the work because the schedule is on track and nothing else has changed and leave the sponsor and governance body out of it entirely
Cut the team size to save money without telling the sponsor or anyone else in charge
Add extra scope to the project in an attempt to make it fit the new strategy
Show the answer
A. Raise the situation with the sponsor and governance body so they can reassess whether to continue
A project exists to serve strategy, so a strategic change must go to the people who decide whether it should continue, change or stop. Being on schedule does not justify delivering something the organization no longer wants.
Reference: PMI PMP Examination Content Outline effective 9 July 2026, Business Environment domain
Which of these is a benefit rather than a deliverable on a distribution-centre project?
A completed and cured ground floor slab
Approved steel shop drawings
Commissioned loading dock doors
Shorter average truck turnaround time
Show the answer
D. Shorter average truck turnaround time
Deliverables are things the project produces. Shorter turnaround is the improvement the owner gains from using them, so it is the benefit. The slab, drawings and doors are all outputs.
Reference: PMI PMP Examination Content Outline effective 9 July 2026, Business Environment domain
A new local rule adds conditions to the stormwater permit while your site work is under way. What is the first sensible step?
Ignore the new condition until the inspector visits the site
Tell the crew to change methods immediately without writing the change down anywhere
Assess the effect on scope, cost and schedule and take it through change control
Ask the owner to cancel the permit and wait for a simpler one
Show the answer
C. Assess the effect on scope, cost and schedule and take it through change control
A regulation change is a change to requirements, so its impact should be assessed and handled through the normal change process. Ignoring it risks a violation, and unrecorded changes lose control of cost and schedule.
Reference: PMI PMP Examination Content Outline effective 9 July 2026, Business Environment domain