TradeExamPro

Pmp construction delivery practice questions

34 questions from the PMP basics for construction practice test.

Start practising

Pmp construction delivery practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Sample questions

On a design-bid-build job, the drawings contain a defect the contractor could not have found by reasonable review. Who generally carries the risk of that design defect as between owner and contractor?

  1. The owner, who supplies the plans and specifications
  2. The contractor, because it signed the construction contract
  3. The lowest bidding subcontractor on the affected trade
  4. Both parties equally, under every kind of construction contract
Show the answer

A. The owner, who supplies the plans and specifications

Under the widely applied US rule, the owner impliedly warrants that plans it furnishes are adequate if followed. The contractor still must follow contract notice and review duties, but it does not usually own the design risk.

Reference: US implied warranty of plans and specifications (Spearin doctrine); contract documents govern

Which contract type leaves most of the cost-overrun risk with the owner?

  1. Firm fixed price
  2. Lump sum with a performance bond
  3. Guaranteed maximum price with a cap
  4. Cost-plus-fee with no upper limit
Show the answer

D. Cost-plus-fee with no upper limit

With cost-plus-fee, the owner reimburses actual costs plus a fee, so overruns flow to the owner. Lump sum and capped GMP place that risk on the builder.

Reference: Construction contract types: cost-plus vs lump sum

A fit-out team works in short cycles and the tenant's representative decides what comes next. In an agile framework, who orders the list of remaining work by value?

  1. The scrum master
  2. The product owner
  3. The superintendent
  4. The estimator
Show the answer

B. The product owner

The product owner owns the prioritized backlog and decides order by value. The scrum master facilitates the process and does not set priorities.

Reference: Agile practice: product owner role and backlog

Other topics