Excavation, Demolition and Heavy Civil Contractor Practice Test

Practice questions on excavation and trenching, utilities, roadway and bridge work, heavy equipment and cranes, demolition and earthwork quantities, built on public OSHA and federal highway rules.

210 questions · 6 topics · start free, no sign-up

Start practising

Mixed practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Timed mock exam

50 questions in 60 minutes, drawn from every topic. No answers shown until the end, then a score, your weakest topics and a review of what you missed.

Practise by topic

Sample questions

A debris chute is steeper than 45 degrees from the horizontal. What does the standard require of it?

  1. It may stay open on one side
  2. It must be fully enclosed
  3. It needs a handrail only
  4. It must be painted yellow
Show the answer

B. It must be fully enclosed

Chutes steeper than 45 degrees must be fully enclosed so falling material cannot escape. A handrail does not contain debris.

Reference: 29 CFR 1926.852(b) (eCFR, current as of November 2026)

A trench is 200 ft long, 4 ft wide and 6 ft deep with vertical sides. How many bank cubic yards must be excavated? Round to one decimal place.

Answer in BCY.

Show the answer

177.8 BCY

Volume = 200 x 4 x 6 = 4,800 cubic feet. Divide by 27: 4,800 / 27 = 177.8 BCY.

Reference: Earthwork estimating practice: bank, loose and compacted volume conversions

A trench is 4 feet 8 inches deep, and the crew plans no protective system. What must be true for that to be allowed?

  1. A competent person finds no cave-in potential
  2. The trench will be open for less than one working day
  3. Everyone inside wears a hard hat and a fall harness
  4. The soil passed a lab test within the past year
Show the answer

A. A competent person finds no cave-in potential

Under 5 feet deep a protective system can be skipped only when a competent person examines the ground and finds no indication of a possible cave-in. Time open, PPE and old test results do not replace that examination. The 4-foot depth still triggers the need for a way out.

Reference: 29 CFR 1926.652(a)(1)(ii)

A crane boom touches an energized power line, but the operator is unhurt and there is no fire. What should the operator do first?

  1. Climb down quickly so the crane can be moved away from the line
  2. Stay in the cab, warn others to stay away, and wait until the utility says the line is dead
  3. Step onto the ground holding the crane's handrail to stay steady
  4. Ask the oiler to pull the boom free using a rope
Show the answer

B. Stay in the cab, warn others to stay away, and wait until the utility says the line is dead

Staying in the cab keeps the operator at one potential, and ground around the machine can be energized. Leaving is only for imminent danger such as fire. Touching the machine and the ground at once can be fatal.

Reference: 29 CFR 1926 Subpart CC (eCFR, current), 1926.1408 (training on contact with a line)

On a granular base, what is the purpose of a prime coat applied before asphalt paving?

  1. It soaks into the base top and helps the asphalt stick
  2. It increases the base depth by about one inch
  3. It cools the base so the new asphalt does not overheat
  4. It replaces the need to compact the base
Show the answer

A. It soaks into the base top and helps the asphalt stick

A prime coat is a low-viscosity liquid asphalt that soaks into the base surface, helps hold fines together and gives the pavement a better connection. It does not add depth, cool the base or replace compaction.

Reference: Highway construction practice: asphalt paving

Exams this helps with

ExamWho runs itWhere
Demolition contractorState boardsUnited States (varies by state)