A pipe is laid at a 2 percent grade for 150 ft. How many feet does it drop from one end to the other?

Answer in ft.

Show the answer

3 ft

Drop = length x slope = 150 x 0.02 = 3.0 ft.

Reference: Grade and slope arithmetic

A sewer starts at an upstream invert elevation of 98.40 ft and runs 240 ft at 0.5 percent. What is the downstream invert elevation, in feet?

Answer in ft.

Show the answer

97.2 ft

Drop = 240 x 0.005 = 1.20 ft. Downstream invert = 98.40 - 1.20 = 97.20 ft.

Reference: Grade and slope arithmetic

A sewer pipe with bell-and-spigot joints is being laid. Where do you start, and which way do the bells face?

  1. Start at the upstream end with bells facing downgrade
  2. Start at the downstream end with bells facing upgrade
  3. Start at the middle and work both ways with bells down
  4. Start at the downstream end with bells facing downgrade
Show the answer

B. Start at the downstream end with bells facing upgrade

Laying starts at the low end and works uphill, with bells facing upgrade. Each new pipe's spigot is pushed into the bell of the pipe already laid, and the bell end sits upstream. Starting upstream or facing bells downgrade makes joints harder to assemble and align to grade.

Reference: Gravity sewer installation practice; manufacturer installation guides