Sample questions
A trench is 4 feet 8 inches deep, and the crew plans no protective system. What must be true for that to be allowed?
A competent person finds no cave-in potential
The trench will be open for less than one working day
Everyone inside wears a hard hat and a fall harness
The soil passed a lab test within the past year
Show the answer
A. A competent person finds no cave-in potential
Under 5 feet deep a protective system can be skipped only when a competent person examines the ground and finds no indication of a possible cave-in. Time open, PPE and old test results do not replace that examination. The 4-foot depth still triggers the need for a way out.
Reference: 29 CFR 1926.652(a)(1)(ii)
A trench 8 feet deep is dug in Type B soil and sloped at the maximum allowable 1:1. The bottom is 3 feet wide. How wide is the trench at the top?
Answer in feet.
Show the answer
19 feet
Type B slope is 1 horizontal to 1 vertical. Each side runs 8 ft x 1 = 8 ft out. Top width = 3 + 8 + 8 = 19 ft. Forgetting one side gives 11 ft.
In the soil classification system, what unconfined compressive strength is needed for cohesive soil to qualify as Type A?
0.5 tons per square foot or less
More than 0.5 but less than 1.5 tons per square foot
1.5 tons per square foot or greater
Strength does not matter, only color and moisture
Show the answer
C. 1.5 tons per square foot or greater
Type A cohesive soil has an unconfined compressive strength of 1.5 tsf or more. The 0.5 tsf or less range is Type C, and the middle range is Type B. Strength is a core measure, not an afterthought.