Earthwork math estimating practice questions

32 questions from the Excavation, demolition, highway and heavy practice test.

Start practising

Earthwork math estimating practice test

10 questions, graded as you go, with the reason for every answer. Start free, no sign-up.

Sample questions

A trench is 200 ft long, 4 ft wide and 6 ft deep with vertical sides. How many bank cubic yards must be excavated? Round to one decimal place.

Answer in BCY.

Show the answer

177.8 BCY

Volume = 200 x 4 x 6 = 4,800 cubic feet. Divide by 27: 4,800 / 27 = 177.8 BCY.

Reference: Earthwork estimating practice: bank, loose and compacted volume conversions

Soil has a swell of 25%. How many loose cubic yards will 100 bank cubic yards of it make after digging?

  1. 75 LCY
  2. 125 LCY
  3. 80 LCY
  4. 100 LCY
Show the answer

B. 125 LCY

Loose volume = bank volume x (1 + swell) = 100 x 1.25 = 125 LCY. Eighty comes from dividing by 1.25, which is the load factor step and not the swell step.

Reference: Earthwork estimating practice: bank, loose and compacted volume conversions

An embankment needs 4,500 compacted cubic yards (CCY). Borrow soil compacts to 0.90 CCY for every 1 BCY dug. How many bank cubic yards must be excavated?

Answer in BCY.

Show the answer

5000 BCY

BCY = CCY / shrinkage factor = 4,500 / 0.90 = 5,000 BCY.

Reference: Earthwork estimating practice: bank, loose and compacted volume conversions