A trench is 200 ft long, 4 ft wide and 6 ft deep with vertical sides. How many bank cubic yards must be excavated? Round to one decimal place.
Answer in BCY.
Show the answer
177.8 BCY
Volume = 200 x 4 x 6 = 4,800 cubic feet. Divide by 27: 4,800 / 27 = 177.8 BCY.
Reference: Earthwork estimating practice: bank, loose and compacted volume conversions
Soil has a swell of 25%. How many loose cubic yards will 100 bank cubic yards of it make after digging?
75 LCY
125 LCY
80 LCY
100 LCY
Show the answer
B. 125 LCY
Loose volume = bank volume x (1 + swell) = 100 x 1.25 = 125 LCY. Eighty comes from dividing by 1.25, which is the load factor step and not the swell step.
Reference: Earthwork estimating practice: bank, loose and compacted volume conversions
An embankment needs 4,500 compacted cubic yards (CCY). Borrow soil compacts to 0.90 CCY for every 1 BCY dug. How many bank cubic yards must be excavated?